Friday, April 18: Borough Hall will be closed in observance of the Good Friday holiday. Trash pickup will operate as scheduled.

Category: PSE&G gas construction updates

Road construction updates: April 14 to April 18

West Cliff Street Parking will not be permitted on both sides of West Cliff Street, between Davenport Street and Ross Street.  A contractor crew will be completing work for Somerville Middle School, from 6 am to 6 pm, Monday, April 14 through Friday, April 18. Union Avenue (Rt. 28) and Roosevelt Place PSE&G will be … Continued

Road construction updates: April 7 to April 11

Somerset Street NJ American Water will be installing a water main at the Somerset Street and Middaugh Street intersection. Expect minor traffic delays during working hours (8 am to 4 pm). Learn more about this project.  Rehill Avenue Our contractor crew will continue working on Rehill Avenue, between Union Avenue and E. Main Street. Road … Continued

Road construction updates: March 31 to April 4

Rehill Avenue Our contractor crew will continue working on Rehill Avenue, between Union Avenue and E. Main Street. Road will remain open, but there will be a single-lane alternating traffic pattern in active work zones. Please plan for delays in this area. PSE&G crews will also be working on Rehill Avenue, near the hospital. They … Continued

PSE&G gas construction update: week of March 24

PSE&G crews continue to work on the gas pipe replacement project. Monday, March 24 to Friday, March 28 Hours: 7 am to 3 pm Monday through Wednesday: Connecting new piping to the gas network (tie-in) in scattered locations Thursday and Friday: Digging pits by the hospital at Rehill Avenue, Cleveland Street, and Lincoln Avenue Traffic … Continued

PSE&G gas construction update: week of March 17

PSE&G crews continue to work on the gas pipe replacement project. Expect detours and limited parking in sections of Main Street. Pedestrian access to all businesses will be maintained. Monday, March 17 to Friday, March 21 Hours: 7 am to 3 pm Digging pits in scattered locations No work planned on Main Street this week … Continued

PSE&G gas construction update: week of March 10

Expect detours and no parking in sections of Main Street, while PSE&G crews work on the gas pipe replacement project. Pedestrian access to all businesses will be maintained. Monday, March 10 to Friday, March 14 Hours: 7 am to 3 pm Main Street (Rt 28), from N. Bridge Street to Maple Street Monday: working in … Continued

PSE&G gas construction update: week of March 3

Expect detours and no parking in sections of Main Street, while PSE&G crews work on the gas pipe replacement project. Pedestrian access to all businesses will be maintained. Monday, March 3 to Friday, March 7 PSE&G crews will work from 7 am to 3 pm on Main Street (parking spaces) Scattered locations to tie-in piping to … Continued

PSE&G gas construction update: week of February 24

Expect detours and no parking in sections of Main Street, while PSE&G crews work on the gas pipe replacement project. Pedestrian access to all businesses will be maintained. Monday, February 24 to Friday, February 28 The overnight crew will work on Main Street, from N. Bridge St to Maple St, until mid-week (date to be … Continued

PSE&G gas construction update: week of February 18

PSE&G and contractor crews are in the final phase of the gas pipe replacement project. Crews will be working on Main Street from January through April. Expect detours and “no parking” signs in sections of Main Street. Pedestrian access to all businesses will be maintained. Tuesday, February 18 to Friday, February 21 PSE&G crews will … Continued

PSE&G gas construction update: week of February 10

PSE&G and contractor crews are in the final phase of the gas pipe replacement project. Crews will be working on Main Street from January through April. Expect detours and “no parking” signs in sections of Main Street. Pedestrian access to all businesses will be maintained. Monday, February 10 to Friday, February 14 The overnight crew … Continued

Close window