PSE&G gas construction update: February 26 week

Posted on February 27, 2024


PSE&G map for the week of February 26

February 27 update: PSE&G crews will not work on Wednesday, February 28, due to the weather forecast. All lanes will be open on Main Street and parking will be permitted until work resumes on Thursday, February 29.

——————————————————————————————–

PSE&G will continue working on the gas pipe replacement project that started in March 2023.

Week of February 26

A PSE&G and contractor crew will complete service appointments on E. Main Street, working from N. Bridge Street to Grove Street. All work is weather permitting. Lane shifts will be used to direct the traffic flow.

Main Street plan

  • Work on Main Street started at the Bridge Street intersection and will end at Park Avenue
  • Work hours are from 9 am to 3 pm (approved by the state)
  • Crews will start setting up at 8 am and complete breakdown by 4 pm
  • Traffic control will include lane shifts, road closures and detours around work areas, to ensure safety
  • “No Parking” signs will be posted on Main Street, from Division Street to Grove Street
    • “No Parking” hours are from 8 am to 4 pm (to accommodate setup and breakdown)
    • Signs will be moved as the work progresses

Questions

Contact the PSE&G Gas Construction customer hotline at 1-833-661-6400 or email GasWorks@PSEG.com.

Close window