PSE&G gas construction map

Plan for road closures in sections of Reimer St, Eastern Ave, E Cliff St, and E High St next week, as PSE&G continues working on the gas pipe replacement project. All work is weather permitting.

Reimer Street

Monday, March 25 and Tuesday, March 26

  • Road will be closed between Vanderveer Ave and N. Gaston Ave, while crews install a gas main
  • No parking on Reimer St (between Eastern Ave and N. Gaston Ave)

Wednesday, March 27 to Friday, March 29

  • Road will be closed between Eastern Ave and N Gaston Ave, while crews install a gas main
  • No parking on Reimer St (between Eastern Ave and N Gaston Ave)

Eastern Avenue

Monday, March 25 to Friday, March 29

Road will be closed between Union Ave and E Cliff St, while crews cross the Reimer St intersection

East Cliff Street and East High Street

Monday, March 25 to Friday, March 29

Roads will be closed between N Gaston Ave and Eastern Ave, while crews install gas mains and connect services

Questions

Contact the PSE&G Gas Construction customer hotline at 1-833-661-6400 or email GasWorks@PSEG.com.