The Borough Hall main entrance and driveway will be closed for approximately 4 weeks, starting on Tuesday, September 23. Please use the library's main entrance to access the building. Also note, Borough Hall will be closed for an employee training event, from 12:30 to 4:30 pm, on Friday, September 26.

PSE&G gas construction update: week of February 18

Posted on February 14, 2025


PSE&G gas construction weekly update

PSE&G and contractor crews are in the final phase of the gas pipe replacement project. Crews will be working on Main Street from January through April. Expect detours and “no parking” signs in sections of Main Street. Pedestrian access to all businesses will be maintained.

Tuesday, February 18 to Friday, February 21

  • PSE&G crews will not work on Monday, February 16 (Presidents Day)
  • The overnight crew will work on Main Street, from N. Bridge St to Maple St
  • The day crew will work in scattered locations, from 7 am to 3 pm, to tie-in piping to the gas system (Tuesday, Thursday and Friday)

Questions

Contact the PSE&G Gas Construction customer hotline at 1-833-661-6400 or email GasWorks@PSEG.com.