PSE&G and contractor crews will continue working on the gas pipe replacement project, on the roads listed below.
Monday, July 1 to Wednesday, July 3
Note: Crews will not work on July 4 and July 5. All work is weather permitting.
- Putnam St: Installing main between N Clark Ave and Post St
- N. Auten Ave: Connecting services between E. Main St and Putnam Ave
- Madison St: Starting after work on N. Auten Ave is completed
View the interactive map showing current work locations.
Questions
Contact the PSE&G Gas Construction customer hotline at 1-833-661-6400 or email GasWorks@PSEG.com.