Rehill Avenue construction notice

Posted on April 24, 2025


Road Construction Notice

Note: Phase 2 (paving) was postponed until May 1 and May 2.

Phase 2 – update

Nighttime milling and paving

Dates: Thursday, April 24 and Friday, April 25 Thursday, May 1 and Friday, May 2
Work Hours:
8 pm to 6 am

  • Rehill Avenue will be divided into 2 sections, with only 1 section scheduled for work each night
  • During working hours, the active work zone will be closed to traffic. The other section will remain open.
  • Detour signs will be posted to assist with traffic flow
  • Schedule is weather-dependent and the start date may be delayed if there’s any inclement weather.

Rehill Avenue map

——————————————————————————————-

Construction on Rehill Avenue, between Union Avenue and E. Main Street, is scheduled to begin on or about Monday, March 24, 2025. The work will be completed in 2 phases by the end of May. Dates are tentative, pending weather.

Phase 1

Starting on or about March 24, 2025
Work hours: 7 am to 5 pm, Monday through Friday

  • Removal and replacement of concrete curb ramps to install new ADA-compliant ramps
  • Curbs, sidewalks, and aprons will be replaced in various locations
  • Traffic Plan: Road will remain open, but there will be a single-lane alternating traffic pattern in active work zones. Please plan for delays in this area.

Phase 2

Starting on or about April 28, 2025 

  • Milling the existing roadway and installing a new asphalt surface course
  • We will notify residents with further details and instructions, prior to the start of this phase

Funding

In 2023, we appropriated $592,800 for improvements to Rehill Avenue. This includes a $494,800 NJDOT grant and $48,000 Developer Infrastructure Trust Funding.

Questions

If you have any questions or concerns, please contact the contractor managing this project.

Top Line Construction Corp
Office Hours: 8:30 am to 5 pm
Phone: 908-231-7570