Note: Updated on August 13 to add PSE&G striping schedule. This street restoration work is part of the gas construction project.
- Date: August 14
 - Work hours: 7:30 am start
 - Locations
- Putnam St (Post St to N. Clark Ave)
 - N. Clark Ave (Main St to Union Ave)
 - S. Clark Ave (Kirby Ave to Main St)
 - S. Adamsville Rd (Central Ave to Main St)
 - S. Auten Ave (Main St to Kirby Ave)
 - Madison St (Adamsville Rd to Eastern Pkwy)
 - S. Richards Ave (Main St to Kirby Ave)
 - N. Richards Ave (Union St to Main St)
 
 
Expect minor traffic delays, as NJ American Water continues installing a water main this week. This work is part of the water main construction project.
- Dates: August 11 to August 15
 - Work hours: 7 am to 3 pm
 - Location: Somerset Street