News

Category
Plan for detours and road closures in sections of N. Gaston Ave, Reimer St and Codington Pl

PSE&G gas construction update: April 29 week

Posted on April 26, 2024

Plan for road closures and detours next week, as PSE&G and contractor crews continue working on the gas pipe replacement project. All work is weather permitting. Reimer Street Monday, April 29 to Wednesday, May 1 Crews will be connecting services between N. Gaston Ave and Eastern Ave Work hours are from 9 am to 2...
PSE&G construction map

PSE&G gas construction update: April 22 week

Posted on April 19, 2024

Plan for road closures and detours next week, as PSE&G and contractor crews continue working on the gas pipe replacement project. All work is weather permitting. N. Gaston Ave Monday, April 22 (8 pm to 6 am) There will be a road closure with detours between Union Ave and Main St PSEG&G will be installing...
PSE&G construction map

PSE&G gas construction update: April 15 week

Posted on April 12, 2024

Plan for road closures and detours next week, as PSE&G and contractor crews continue working on the gas pipe replacement project. All work is weather permitting. N. Gaston Ave There will be a road closure with detours between Union Ave and Main St Work hours: Monday, April 15 to Thursday, April 18, from 8 pm...
PSE&G construction map

PSE&G gas construction update: April 8 week

Posted on April 6, 2024

Plan for road closures and detours next week, as PSE&G and contractor crews continue working on the gas pipe replacement project. All work is weather permitting. N. Gaston Ave There will be a lane shift with detours between Union Ave and Main St Work hours are from 8 pm to 6 am PSEG&G will be...
PSE&G gas construction map

PSE&G gas construction update: March 25 week

Posted on March 22, 2024

Plan for road closures in sections of Reimer St, Eastern Ave, E Cliff St, and E High St next week, as PSE&G continues working on the gas pipe replacement project. All work is weather permitting. Reimer Street Monday, March 25 and Tuesday, March 26 Road will be closed between Vanderveer Ave and N. Gaston Ave,...
road construction notice

PSE&G gas construction update: March 18 week

Posted on March 15, 2024

PSE&G is completing post-construction restoration work for the gas pipe replacement project that started in March 2023. All work is weather permitting. Traffic impact This work does not include road closures, but parking will be restricted in active work areas. Please pay attention to posted signs. Crews will be working on: 2nd St 3rd St Brookside...
road construction notice

PSE&G gas construction update: March 11 week

Posted on March 9, 2024

On March 12, PSE&G contractor crews will start restoration on all the services they completed on E. Main Street, from Park Avenue down to N. Bridge Street. This work will not impact traffic, as they will be working on the side of the road. No parking signs will be posted where the crews are working....
PSE&G construction map

PSE&G gas construction update: March 4 week

Posted on March 1, 2024

UPDATE: Due to the weather forecast, PSE&G contractor crews will not work on Main Street on Tuesday, March 5. All traffic lanes will be open. We are waiting for PSE&G to confirm if work will continue on E. High Street. PSE&G will continue working on the gas pipe replacement project that started in March 2023....
PSE&G map for the week of February 26

PSE&G gas construction update: February 26 week

Posted on February 27, 2024

February 27 update: PSE&G crews will not work on Wednesday, February 28, due to the weather forecast. All lanes will be open on Main Street and parking will be permitted until work resumes on Thursday, February 29. -------------------------------------------------------------------------------------------- PSE&G will continue working on the gas pipe replacement project that started in March 2023. Week of...

PSE&G gas construction update: February 20

Posted on February 16, 2024

2/22 Update: PSE&G will not work on Main Street on Friday, February 23. This change is due to the weather forecast. ------------------------------------------------------------------------------------------------------------ Main Street Update: PSE&G will be connecting services on Main Street, from N. Bridge Street to Grove Street, on February 22 and 23. Traffic will shift over in both directions to allow work...
road construction notice

PSE&G gas construction update: February 14

Posted on February 9, 2024

February 15 update: Crews will work on E. Main Street, near Hamilton Street, on Thursday and Friday. February 14 update: Work was postponed due to inclement weather and will resume on Thursday, February 15. -------------------------------------------- PSE&G crews will start working on Main Street at 9 am, on Monday, February 12. This work is to connect...
PSE&G construction map

PSE&G gas construction update: December 18

Posted on December 15, 2023

PSE&G and contractor crews are working in Somerville to replace gas mains and services. Monday, December 18 to Friday, December 22 E. Cliff  St (between Culver St and N. Gaston Ave): Installing main and connecting services Culver St (between E High St and E Cliff St): Installing main and connecting services Note: PSE&G picked up...
PSE&G construction map

PSE&G gas construction update: December 11

Posted on December 8, 2023

PSE&G and contractor crews are working in Somerville to replace gas mains and services. Monday, December 11 to Friday, December 15 E. Cliff  St (between Culver St and N. Gaston Ave): Installing main and connecting services Culver St (between E High St and E Cliff St): Installing main and connecting services About this project This...
PSE&G construction map

PSE&G gas construction update: December 4

Posted on December 1, 2023

PSE&G is working in Somerville to replace gas mains and services. Monday, December 4 to Friday, December 8 E. Cliff  St (between Culver St and N. Gaston Ave): Installing main and connecting services Culver St (between E High St and E Cliff St): Installing main and connecting services About this project This work is Phase...
PSE&G map week of November 20

PSE&G gas construction update: November 20

Posted on November 20, 2023

Monday, November 20 to Wednesday, November 22 E. Cliff St (between Culver St and N. Gaston Ave): Installing main and connecting services Culver St (between Bartine St and E. Cliff St): Installing main and connecting services Additional Locations: PSEG will notify Somerville Police as the week progresses We do not expect crews to work on November...
PSE&G gas construction map

PSE&G gas construction update: November 13

Posted on November 13, 2023

Main St update: PSE&G will not work overnight on Thursday, November 16. They will work overnight on Friday, November 17, starting at about 7 pm. Plan for lane shifts and no parking from Maple St to Grove St. This is the last day for night work until January. Monday, November 13 to Saturday, November 18 Main...
November 6 construction map

PSE&G Gas Construction Update: November 6

Posted on November 6, 2023

PSE&G is planning to add more locations this week. They will notify Somerville Police who will redirect traffic, as needed. Monday, November 6 to Saturday, November 11 Main Street (N. Bridge St intersection): OVERNIGHT on Wednesday and Thursday. Lane shifts (Maple St to Grove St), from 8 pm to 5 am, with traffic control setting...
map showing the streets where construction is happening

PSE&G Gas Construction Update: October 30

Posted on October 30, 2023

PSE&G is working in Somerville to replace gas mains and services. This work is Phase 1 of a 10-12 month gas construction project. All crews will first finish installing new mains and then proceed to connect service lines. Expect an increase in traffic, loud noise, and presence of heavy equipment and machinery in these areas. All...

PSE&G Gas Construction Update: October 23

Posted on October 23, 2023

PSE&G is working in Somerville to replace gas mains and services. This work is Phase 1 of a 10-12 month gas construction project. All crews will first finish installing new mains and then proceed to connect service lines. Expect an increase in traffic, loud noise, and presence of heavy equipment and machinery in these areas. All...
October 16 construction map

PSE&G Gas Construction Update: October 16

Posted on October 16, 2023

PSE&G is working in Somerville to replace gas mains and services. This work is Phase 1 of a 10-12 month gas construction project. All crews will first finish installing new mains and then proceed to connect service lines. Expect an increase in traffic, loud noise, and presence of heavy equipment and machinery in these areas. All...
Close window