PSE&G is working in Somerville to replace gas mains and services. This work is Phase 1 of a 10-12 month gas construction project. All crews will first finish installing new mains and then proceed to connect service lines.
Expect an increase in traffic, loud noise, and presence of heavy equipment and machinery in these areas. All work is pending weather and availability of materials.
Monday, September 11 to Saturday, September 16
Pay attention to posted street signs for any changes.
- Grove St (between E Young St and Rt 22): Connecting services
- Maple St (between W High St and W Main St): Connecting services
- Main St (between James St and Loeser Ave): Replacing main and connecting services
- Vanderveer Ave (between Reimer St and Grant Ave): Replacing main and connecting services
Garbage collection
Plan for an earlier pickup while roads are under construction. Please put trash out the night before collection.
Questions and concerns
Contact the Gas Construction Customer Hotline at 1-833-661-6400 or gasworks@pseg.com.